Notice of Night Permit Application

Mortenson | Clark will be applying for a Night Permit to perform the installation of drilled shaft foundations at extended work hours, from 7:00 AM to 11:00 PM. Work associated to this application will take place select days between July 26, 2017 and September 5, 2017. Work dates associated to the application do not include Sunday(s) or Labor Day.

Mission Bay CAC

Mortenson | Clark, GSW, and OCII will be attending the Monthly Mission Bay Citizen Advisory Committee Meeting July 13, 2017 to provide a construction update.

The meeting will take place at 5:00 PM at 225 Berry Street, San Francisco, CA (Creek Room), and is open to any interested.

Procurement Package #3 – Timeline

Please see the following timeline for the updated calendar events/dates related to Procurement Package #3 for the Chase Center project.

RFQ Issued: July 26, 2017
RFQ Due Date: August 10, 2017
Meet the Prime/SBE Matchmaking Session: August 24, 2017
RFP Released: September 12, 2017
Pre-Proposal Meeting: September 26, 2017
RFP Due: October 17, 2017